To address Europe's future energy demand, significant investments into hydrogen infrastructure are essential. One of the core components of this initiative is the development of a pan-European hydrogen pipeline network in the North Sea, designed to connect major hydrogen producers with key consumers across the continent. The AquaDuctus project is part of this future pipeline network. The AquaDuctus project consists of an offshore part (Exclusive Economic Zone (EEZ) and territorial waters of the German North Sea at the coastline of Lower Saxony) and an onshore part with a receiving terminal to make connection with the onshore grid.
The AquaDuctus project is planned as a large diameter pipeline (48 inch) with a transport capacity of 20 GWH2 and a design pressure of 120 bar. The conceptual design of the pipeline enables the connection of neighbouring European hydrogen infrastructures and the planned production facilities in the German EEZ (SEN-1 Area).
Geophysical and geotechnical survey is required for the FEED stage design and construction planning of the proposed offshore platform.
The geophysical survey scope includes multi-beam echosounder (MBES), side-scan sonar (SSS), shallow sub-bottom profiling (SBP), 2-Dimentional Ultra-High Resolution Seismic (2DUHRS) and magnetometer/ gradiometer.
The geophysical survey will produce detailed subsurface mapping, which is critical for the evaluation of geohazards, foundation selection, and offshore platform location feasibility. The geophysical survey shall take place prior to the geotechnical survey.
The geotechnical survey scope consists of deep geotechnical boreholes and Cone Penetrometer Tests with pore pressure (CPTu).
The geotechnical survey will provide deep intrusive geotechnical data through detailed logging, in-situ testing, sampling and laboratory testing of selected samples.
This tender includes the following survey scopes: Offshore Platform - Geophysical Survey and Offshore Platform - Geotechnical Survey.
For a detailed scope of work, see Attachment B.1 Scope of Work (that will be shared after A.4 Non Disclosure Agreement is signed).